A & E Property - Conversion Project

Kingfisher Conversion

This project was presented to A & E Property off market and it consisted of a conversion element of an existing 3 bedroom house into two units comprising of a 1 bedroom house and a 2 bedroom house. The conversion was managed by A & E Property LTD using our builders to make adjustments to the floor plans and areas to separate the two units safely and securely.


Videos


Project Timeline

  • Offer Accepted

    7th August 2018

    Initial offer accepted.

  • Works Started

    5th November 2018

    Tendering process complete and works commencing from today.

  • Property Complete and Let out

    26th March 2019

    Conversion completed and signed off by building control with all of its own utility connections.